Estudio técnico económico de alternativas del proceso de cimbrado y descimbrado en la construcción de un edificio de forjados de losa maciza de hormigón armado

Y. Alvarado, I. Gasch, P. Calderón, B. Torres

Producción: Contribución a una revistaArtículorevisión exhaustiva

4 Citas (Scopus)

Resumen

The aim of this paper is to define alternative construction processes for a building with reinforced concrete slab floors, thereby estimating which ones are most beneficial in terms of their execution time and cost. Three alternatives were proposed to solve the deadlines of the construction process: Shoring and Striking; Shoring, Clearing and Striking; and Shoring, Reshoring and Striking, considering 2, 3 and 4 consecutive shored floors. In order to evaluate what processes are valid, first it is necessary to calculate the loads during the construction process using the New Simplified Procedure and subsequently check whether or not the striking condition is fulfilled in each of the construction operations. Regarding the studied building, the feasible construction processes were: Shoring, Clearing and Striking with 3 and 4 consecutive shored floors.

Título traducido de la contribuciónStudy of technical and economical alternatives of a shoring and striking process during the construction of a building with reinforced concrete slab floors
Idioma originalEspañol
Páginas (desde-hasta)117-126
Número de páginas10
PublicaciónRevista Ingenieria de Construccion
Volumen31
N.º2
DOI
EstadoPublicada - ago. 2016

Palabras clave

  • Clearing
  • Construction process
  • Load transmission
  • New simplified procedure
  • Shores

Huella

Profundice en los temas de investigación de 'Estudio técnico económico de alternativas del proceso de cimbrado y descimbrado en la construcción de un edificio de forjados de losa maciza de hormigón armado'. En conjunto forman una huella única.

Citar esto