Estimation of shore removal times in bi-directional in situ concrete floor slabs applying the maturity method

Yezid A. Alvarado, Pedro A. Calderón, Francisco J. Pallarés, Teresa Pellicer

Producción: Capítulo del libro/informe/acta de congresoContribución a la conferenciarevisión exhaustiva

2 Citas (Scopus)

Resumen

This article puts forward a methodology for estimating timing for the removal of shoring on cast-in-place two-way concrete slabs under flexural load, while seeking to guarantee withstanding final and serviceable thresholds during the construction stage. To do this, the development of concrete properties is evaluated at very early ages using the concrete maturity method. Thus, when tensile strength is required at a certain stage in the construction, it is necessary to evaluate the required timing for a new stage of shoring and the removal of shoring for floor slabs at a range of temperatures and for different types of concrete. The conditions for shoring removal are also established from the compressive strength in relation to tensile strength by experimenting with certain formulas. The timing for partial shoring removal for a floor can thus be estimated. Partial shoring removal involves removing formwork and intermediate props (known as "clareado" ["clearing"], a construction practice commonly used in Spain). Timing for complete shoring removal for the floor is established in the same way.

Idioma originalInglés
Título de la publicación alojadaConstruction and Professional Practices - Proceedings of the 10th East Asia-Pacific Conference on Structural Engineering and Construction, EASEC 2010
EditorialSchool of Engineering and Technology
Páginas55-60
Número de páginas6
ISBN (versión impresa)9748257207, 9789748257204
EstadoPublicada - 2006
Publicado de forma externa
Evento10th East Asia-Pacific Conference on Structural Engineering and Construction, EASEC 2010 - Bangkok, Tailandia
Duración: 03 ago. 200605 ago. 2006

Serie de la publicación

NombreConstruction and Professional Practices - Proceedings of the 10th East Asia-Pacific Conference on Structural Engineering and Construction, EASEC 2010
Volumen5

Conferencia

Conferencia10th East Asia-Pacific Conference on Structural Engineering and Construction, EASEC 2010
País/TerritorioTailandia
CiudadBangkok
Período03/08/0605/08/06

Huella

Profundice en los temas de investigación de 'Estimation of shore removal times in bi-directional in situ concrete floor slabs applying the maturity method'. En conjunto forman una huella única.

Citar esto