Delay Factors: A Comparative Analysis between Road Infrastructure and Building Projects

Omar Sánchez, Karen Castañeda, Guillermo Mejía, Eugenio Pellicer

Producción: Capítulo del libro/informe/acta de congresoContribución a la conferenciarevisión exhaustiva

8 Citas (Scopus)

Resumen

Delay is one of the most common, complex, and risky phenomena that adversely affects performance of construction projects. Several studies have been conducted on delay factors identification, some focused on road infrastructures, others on buildings, or on construction projects broadly. However, there are scarce publications with a comprehensive and sound analysis among projects of different type. This study presents a comparative analysis of delay factors between road infrastructure and building projects using the following research process: (1) a systematic review of articles published in specialized and peer-reviewed journals is performed; 2) relevant studies are chosen based on inclusion/exclusion criteria; (3) qualitative evidence is categorized; (4) quantitative evidence is analyzed with Spearman's rank correlation coefficient; and (5) contributions are summarized. A final set of twenty published articles provided quantitative and qualitative evidence of construction delays. The findings indicated that delay factors identification and prioritization differs between projects and countries. Some critical delay factors for road infrastructure projects were inadequate contractor's experience and payment delays to contractor, while for building projects were shortage of materials and financial difficulties of contractor.

Idioma originalInglés
Título de la publicación alojadaConstruction Research Congress 2020
Subtítulo de la publicación alojadaProject Management and Controls, Materials, and Contracts - Selected Papers from the Construction Research Congress 2020
EditoresDavid Grau, Pingbo Tang, Mounir El Asmar
EditorialAmerican Society of Civil Engineers (ASCE)
Páginas223-231
Número de páginas9
ISBN (versión digital)9780784482889
EstadoPublicada - 2020
Publicado de forma externa
EventoConstruction Research Congress 2020: Project Management Controls, Materials, Contracts - Tempe, Estados Unidos
Duración: 08 mar. 202010 mar. 2020

Serie de la publicación

NombreConstruction Research Congress 2020: Project Management and Controls, Materials, and Contracts - Selected Papers from the Construction Research Congress 2020

Conferencia

ConferenciaConstruction Research Congress 2020: Project Management Controls, Materials, Contracts
País/TerritorioEstados Unidos
CiudadTempe
Período08/03/2010/03/20

Huella

Profundice en los temas de investigación de 'Delay Factors: A Comparative Analysis between Road Infrastructure and Building Projects'. En conjunto forman una huella única.

Citar esto