Estimation of shore removal times in bi-directional in situ concrete floor slabs applying the maturity method

Research output: Chapter in Book/Report/Conference proceedingConference contributionpeer-review

2 Scopus citations

Abstract

This article puts forward a methodology for estimating timing for the removal of shoring on cast-in-place two-way concrete slabs under flexural load, while seeking to guarantee withstanding final and serviceable thresholds during the construction stage. To do this, the development of concrete properties is evaluated at very early ages using the concrete maturity method. Thus, when tensile strength is required at a certain stage in the construction, it is necessary to evaluate the required timing for a new stage of shoring and the removal of shoring for floor slabs at a range of temperatures and for different types of concrete. The conditions for shoring removal are also established from the compressive strength in relation to tensile strength by experimenting with certain formulas. The timing for partial shoring removal for a floor can thus be estimated. Partial shoring removal involves removing formwork and intermediate props (known as "clareado" ["clearing"], a construction practice commonly used in Spain). Timing for complete shoring removal for the floor is established in the same way.

Original languageEnglish
Title of host publicationConstruction and Professional Practices - Proceedings of the 10th East Asia-Pacific Conference on Structural Engineering and Construction, EASEC 2010
PublisherSchool of Engineering and Technology
Pages55-60
Number of pages6
ISBN (Print)9748257207, 9789748257204
StatePublished - 2006
Externally publishedYes
Event10th East Asia-Pacific Conference on Structural Engineering and Construction, EASEC 2010 - Bangkok, Thailand
Duration: 03 Aug 200605 Aug 2006

Publication series

NameConstruction and Professional Practices - Proceedings of the 10th East Asia-Pacific Conference on Structural Engineering and Construction, EASEC 2010
Volume5

Conference

Conference10th East Asia-Pacific Conference on Structural Engineering and Construction, EASEC 2010
Country/TerritoryThailand
CityBangkok
Period03/08/0605/08/06

Keywords

  • Clearing
  • Concrete
  • Construction
  • Formwork
  • Maturity method
  • Props
  • Shoring

Fingerprint

Dive into the research topics of 'Estimation of shore removal times in bi-directional in situ concrete floor slabs applying the maturity method'. Together they form a unique fingerprint.

Cite this