Delay Factors: A Comparative Analysis between Road Infrastructure and Building Projects

  • Omar Sánchez
  • , Karen Castañeda
  • , Guillermo Mejía
  • , Eugenio Pellicer
  • Universidad Industrial de Santander
  • Polytechnic University of Valencia

Research output: Chapter in Book/Report/Conference proceedingConference contributionpeer-review

10 Scopus citations

Abstract

Delay is one of the most common, complex, and risky phenomena that adversely affects performance of construction projects. Several studies have been conducted on delay factors identification, some focused on road infrastructures, others on buildings, or on construction projects broadly. However, there are scarce publications with a comprehensive and sound analysis among projects of different type. This study presents a comparative analysis of delay factors between road infrastructure and building projects using the following research process: (1) a systematic review of articles published in specialized and peer-reviewed journals is performed; 2) relevant studies are chosen based on inclusion/exclusion criteria; (3) qualitative evidence is categorized; (4) quantitative evidence is analyzed with Spearman's rank correlation coefficient; and (5) contributions are summarized. A final set of twenty published articles provided quantitative and qualitative evidence of construction delays. The findings indicated that delay factors identification and prioritization differs between projects and countries. Some critical delay factors for road infrastructure projects were inadequate contractor's experience and payment delays to contractor, while for building projects were shortage of materials and financial difficulties of contractor.

Original languageEnglish
Title of host publicationConstruction Research Congress 2020
Subtitle of host publicationProject Management and Controls, Materials, and Contracts - Selected Papers from the Construction Research Congress 2020
EditorsDavid Grau, Pingbo Tang, Mounir El Asmar
PublisherAmerican Society of Civil Engineers (ASCE)
Pages223-231
Number of pages9
ISBN (Electronic)9780784482889
StatePublished - 2020
Externally publishedYes
EventConstruction Research Congress 2020: Project Management Controls, Materials, Contracts - Tempe, United States
Duration: 08 Mar 202010 Mar 2020

Publication series

NameConstruction Research Congress 2020: Project Management and Controls, Materials, and Contracts - Selected Papers from the Construction Research Congress 2020

Conference

ConferenceConstruction Research Congress 2020: Project Management Controls, Materials, Contracts
Country/TerritoryUnited States
CityTempe
Period08/03/2010/03/20

Fingerprint

Dive into the research topics of 'Delay Factors: A Comparative Analysis between Road Infrastructure and Building Projects'. Together they form a unique fingerprint.

Cite this