Aplicación del método de la madurez para la estimación del plazo de descimbrado de forjados construidos con sistemas industrializados

Translated title of the contribution: Application of the maturity method for the estimation of shore removal times in concrete floor slabs built with industrial systems

M. C. Castro-Garrido, M. C. López-Garzón, Y. A. Alvarado, J. O. Castaño, I. Gasch

Research output: Contribution to journalArticlepeer-review

2 Scopus citations

Abstract

This article proposes a methodology for estimating the striking time for reinforced concrete slab floors build with industrial systems. For this, a study of maturity of concrete used in such construction is performed. To make the maturity curve in the laboratory, the methodology described in ASTM C1074 is implemented by calculating the activation energy for the three proposed methods and measuring the thermal history of the concrete at a controlled temperature. Finally, a reinforced concrete slab floor is monitored and the striking time is estimated. It has been observed that the final setting time is not recommended for striking slabs floors, as recommended by the manufacturers of concrete in Colombia. Striking time obtained is higher than the final setting time, having a difference of up to 11 hours at the most critical case.

Translated title of the contributionApplication of the maturity method for the estimation of shore removal times in concrete floor slabs built with industrial systems
Original languageSpanish
Article numbere131
JournalInformes de la Construccion
Volume68
Issue number541
DOIs
StatePublished - 2016

Fingerprint

Dive into the research topics of 'Application of the maturity method for the estimation of shore removal times in concrete floor slabs built with industrial systems'. Together they form a unique fingerprint.

Cite this